Footing Crews Laying Foundations…vertical construction starts soon.

This week our footing crews started the foundations for the vertical construction once the pad was completed and accepted.

Our civil work continue to progress in and around the weather cycles. While our foundation crews poured out the east footing early this week for the bridge, the remainder of the crew was finishing up H-piles on the center footing. Our plans are to pour the center footing the first of the week. The arch structure is scheduled for delivery next week with erection to follow.

The concrete crews also poured the headwall for the outlet end of the triple 72” pipes.