Concrete and Metal Installed at Gastonia

 

Crews installing concrete pipe

Storm crews installing storm pipe through the basket wall, which when complete will discharge drainage from nearby areas and to the relocated Duhart’s Creek.

 

Truck turnaround area and loading dock shown

Crews finishing up the truck turn around concrete paving; this area will allow full access to the load dock for delivery to the building as it is now completed.

 

Curbing Crews Working on north side of site

Our crews have placed curb on the North side of the building and in the eastern side of the parking lot including completing almost 3,000 linear feet in one day.

 

Excavation for raft footing

Crews are excavating for the raft foot to support the basket wall. This leg of the wall runs to approximately where the trucks are sitting in the picture. At that point the wall changes to a concrete-covered soil nail wall.

 

Site Overview of Civil Operations

The construction of bridge and wall backfill areas are shown above as crews perform their various assigned tasks.

 

Entrance and Blade Tower

The blade tower and front entrance is nearing completion. EIFS was finished last week and now the crews are working on the metal studding for the façade and over the entrance area.

 

Left side and rear of building

The rear and side elevations were finished and the fine grading near completion around the building. There is still a lot of work to be done, but Gastonia takes one more step towards completion each day.