Grading Stones and sidewalks started at Gastonia

 

Crews prepping subgrade

Crews worked all week prepping subgrade and getting the north main drive ready for stone. Some areas required an undercut after not passing proof roll initially.

 

Motorgrader spreading stone

Stone was used to spread the roads around the site to bring to grade. A motorgrader was used to spread the stone. The crews used water to assist in making sure that the optimum density is achieved.

 

Roller used to compact the stone

A roller was used in the final step to compact the stone. The density requirement for the stone is 100% per AASHTO T99 standards.

 

Crews working on last bits of parking lot area

Crews working on last bits of parking lot area

Site crews have worked to get the last lifts of fill in the parking lot area so that concrete curb and gutter can be poured. The crews will fine-grade the parking lot for stone after the curb and gutter is done.

 

Crews relaying material to center of arches

The crews installed a 55 foot wide raft that the basket walls sit on. The white fabric is a high strength geotextile material that wraps the raft.

 

Top Soil installation in planters

Landscape crew installed the topsoil mix for the planter boxes in the front of the building. There is 3’ of topsoil over a 12” layer of stone. The fabric that covers the stone is for filtration purposes only. It acts as a barrier between the stone and topsoil.

Crews relaying material to center of arches

Bailing material was placed in the center of the arches by a larger excavator as a mini-excavator placed it for compaction. This is a very slow process, but with the two crews working together it is progressing nicely.

 

Crews working on sidewalk forms

Sidewalk forms for rear of building

Sidewalks are beginning to take shape and the crews are slated to start the pours this week. Preparation was completed last Friday.

 

Crews finishing walls for painters

Backer rods and colored caulk was completed on the outside of the building and as they finish, the painters are right behind them priming the walls.

 

Paint Crew Priming Wall

Paint crews began priming the outside walls of the building and as of last Friday had completed 3 sides. The painting will begin this week as they finalize the last wall.

 

Framework for guest services area

Blocking and framework has been completed in entrance and guest services area. Drywall was started and is on track to finish on schedule.