Gastonia Channels Forward
The channel defining process began with the crews staking out the new channel and started to install the rock vain on the downstream side of the arches.
Rock vein is installed and the crew is working on the riffle section going under the arch. There will be 13 of these structures to be installed in the new channel.
Over 2,000 linear feet of concrete curbs was poured by the Curb crews. There is around 800 linear feet left to pour in the parking lot and will be finished next week.
Fine grade crews are working to get parking lot grades cut and stone placed. This is the main drive on the east side of the parking lot.
The Storefront is coming along nicely. Glass is being installed, as well as some of the sidewalk signs.
We are finishing up our sidewalk prep work with lights, tree grates and bollard sleeves.
We have also started our tile installation. Once all the pieces have been cut out for columns and sprinklers the tile will go up fast.
In the Food Ave area sheet rock is up, mud is being applied and paint will soon follow.