Gastonia Channels Forward

2011 May 31

New channel staked

The channel defining process began with the crews staking out the new channel and started to install the rock vain on the downstream side of the arches.

 

Rock vein installation

Rock vein is installed and the crew is working on the riffle section going under the arch. There will be 13 of these structures to be installed in the new channel.

 

Curb crews pouring concrete

Over 2,000 linear feet of concrete curbs was poured by the Curb crews. There is around 800 linear feet left to pour in the parking lot and will be finished next week.

 

Main Drive of Parking Lot

Fine grade crews are working to get parking lot grades cut and stone placed. This is the main drive on the east side of the parking lot.

 

Glass installation shown

The Storefront is coming along nicely. Glass is being installed, as well as some of the sidewalk signs.

 

Sidewalk for front of building

We are finishing up our sidewalk prep work with lights, tree grates and bollard sleeves.

 

Ceiling Tile Installation

We have also started our tile installation. Once all the pieces have been cut out for columns and sprinklers the tile will go up fast.

 

Food Area Sheet Rock installed

In the Food Ave area sheet rock is up, mud is being applied and paint will soon follow.

 

 

 

 