Progress On All Fronts

2011 June 21

Crews started the soil nail wall this week. This is the first part of the wall, and provides structure for the concrete that will be poured later.

Crews continue to cover subgrade with stone.

The off-site mitigation work is looking good. All the grading is complete with 75% of the small plantings in place. The larger plantings will be done next week.

Crews started the demolition of the concrete median for the offsite roadway improvements.  The crew will have to work closely with the NCDOT and the resurface contract, to be completed at the same time.

Stone crews yield way to paving crews as the first lift of asphalt is put down in the parking lot.