Welcome to Greeting From Gastonia

Welcome to Greetings From Gastonia, an online diary containing posts, images and videos of construction of the redevelopment final phase of the Gaston Mall located in Gastonia, North Carolina. Join us as we create a positive environmental impact story that will serve the local community for years to come. [Read more…]

Work Continues For Gastonia

The site grading contractor has been taking advantage of the great weather in late October to get a jump on the undercut for the future building pad. Multiple layers of grid and stone are being used to insure a stable building foundation.

Granular Material and Fabric Covering

Through the month of October, the site contractor has progressed with the installation of the triple 72”CMP (Corrugated Metal Pipe). This is being installed to relocate an existing storm stream under the future parking lot area.

Forming of 72" Pipe Collar

The relocation of the existing outfall sewer was a 24/7 operation after finding the condition of the existing VCP pipe. Crews worked round the clock for 7 days to install, test and cut over more than 1200lf of new 18” sewer line.

Sewer Crew Setting Up For Relocation Process

Night Work for Sewer Relocation

The site contractor was able to get the transition collar from CMP to RCP in on the triple 72” pipes before the Thanksgiving Holiday.