Weather Slows Progress

The weather did not help the progress of the project any this week due to rainfall totals of almost three inches. The site contractor spent most of the week working on erosion control.

Site View of Erosion Control Maintenance

They were able to get things going later in the week continuing with the triple 72” CMP and the overburden removal.

Triple 72" CMP heads toward stream intersection

Stockpiling Under Cut for Backfill

Undercut Stock Pile Being Loaded Out

Saturday’s work schedule was cut short due to sleet and rain.

Welcome to Greeting From Gastonia

Welcome to Greetings From Gastonia, an online diary containing posts, images and videos of construction of the redevelopment final phase of the Gaston Mall located in Gastonia, North Carolina. Join us as we create a positive environmental impact story that will serve the local community for years to come. [Read more…]