Finalizing Site Work

As the site nears completion, we are cleaning up any signs of a construction site. This stockpile on Outparcel A is being hauled offsite.

We are installing fabric and the pipe under drain system for the Bio retention pond.

Concrete footers are being poured for storm pipe boxes on the Cox Road widening.

Retention Pond, Steam Relocation and Indoor Fixturing Move Ahead

We have begun excavation for the bio retention pond. This landscaping feature will be adapted to treat stormwater runoff on the site.

Along Jett Lanier Drive, our team is working to complete retaining walls.

We are progressing with stream relocation.  The channel has been completed in this section, and pools are being excavated in the flood plain area.

Outside the retail store, trees we have planted trees. Grates will be installed around the base to enhance the look and to keep them from getting damaged.

The  stock room area is almost complete, and we have also made great progress with fixturing.