Gastonia Channels Forward

New channel staked

The channel defining process began with the crews staking out the new channel and started to install the rock vain on the downstream side of the arches.

 

Rock vein installation

Rock vein is installed and the crew is working on the riffle section going under the arch. There will be 13 of these structures to be installed in the new channel.

 

Curb crews pouring concrete

Over 2,000 linear feet of concrete curbs was poured by the Curb crews. There is around 800 linear feet left to pour in the parking lot and will be finished next week.

 

Main Drive of Parking Lot

Fine grade crews are working to get parking lot grades cut and stone placed. This is the main drive on the east side of the parking lot.

 

Glass installation shown

The Storefront is coming along nicely. Glass is being installed, as well as some of the sidewalk signs.

 

Sidewalk for front of building

We are finishing up our sidewalk prep work with lights, tree grates and bollard sleeves.

 

Ceiling Tile Installation

We have also started our tile installation. Once all the pieces have been cut out for columns and sprinklers the tile will go up fast.

 

Food Area Sheet Rock installed

In the Food Ave area sheet rock is up, mud is being applied and paint will soon follow.

 

 

 

 

Paint & Paving at Gastonia

 

Loader spreading stone before paving

North driveway getting the binder asphalt placed.

Stone crews did the final grading and compacting for the north driveway. The drive is tested and once it passes, the asphalt binder is placed.

Service drive after paving

A view of the north driveway from the loading dock

Crews placed the asphalt binder along the north service roads towards the loading dock. In addition, paving was done along the areas near the main entrances.

Concrete crews working on sidewalks

After the weather event last week, concrete crews were able to make pours for the front sidewalk areas. Despite the weather being stubborn, the crews have made great progress.

Loading Docks Shown here

The back area of the building is nearing completion as well. All areas have been primed and painted. In addition, the concrete crews have finished the back side walk pours.

Arches and basket wall shown

Crews are up to the top of the arches with the basket walls.  They have 8 more feet to the top of the wall.

Wiring for ceiling grid shown.

The interior work is progressing as well. Ceiling grid wires have been started and we plan to continue with ceiling grid installation on 5/18/11.

Drywall on sales floor shown taped and bedded.

Walls shown after mudding and tape process

The interior walls were taped and mudded after metal studs were completed last week. Here the walls are shown after this process; ready for final sanding and primer.

 

Grading Stones and sidewalks started at Gastonia

 

Crews prepping subgrade

Crews worked all week prepping subgrade and getting the north main drive ready for stone. Some areas required an undercut after not passing proof roll initially.

 

Motorgrader spreading stone

Stone was used to spread the roads around the site to bring to grade. A motorgrader was used to spread the stone. The crews used water to assist in making sure that the optimum density is achieved.

 

Roller used to compact the stone

A roller was used in the final step to compact the stone. The density requirement for the stone is 100% per AASHTO T99 standards.

 

Crews working on last bits of parking lot area

Crews working on last bits of parking lot area

Site crews have worked to get the last lifts of fill in the parking lot area so that concrete curb and gutter can be poured. The crews will fine-grade the parking lot for stone after the curb and gutter is done.

 

Crews relaying material to center of arches

The crews installed a 55 foot wide raft that the basket walls sit on. The white fabric is a high strength geotextile material that wraps the raft.

 

Top Soil installation in planters

Landscape crew installed the topsoil mix for the planter boxes in the front of the building. There is 3’ of topsoil over a 12” layer of stone. The fabric that covers the stone is for filtration purposes only. It acts as a barrier between the stone and topsoil.

Crews relaying material to center of arches

Bailing material was placed in the center of the arches by a larger excavator as a mini-excavator placed it for compaction. This is a very slow process, but with the two crews working together it is progressing nicely.

 

Crews working on sidewalk forms

Sidewalk forms for rear of building

Sidewalks are beginning to take shape and the crews are slated to start the pours this week. Preparation was completed last Friday.

 

Crews finishing walls for painters

Backer rods and colored caulk was completed on the outside of the building and as they finish, the painters are right behind them priming the walls.

 

Paint Crew Priming Wall

Paint crews began priming the outside walls of the building and as of last Friday had completed 3 sides. The painting will begin this week as they finalize the last wall.

 

Framework for guest services area

Blocking and framework has been completed in entrance and guest services area. Drywall was started and is on track to finish on schedule.

 

 

Concrete and Metal Installed at Gastonia

 

Crews installing concrete pipe

Storm crews installing storm pipe through the basket wall, which when complete will discharge drainage from nearby areas and to the relocated Duhart’s Creek.

 

Truck turnaround area and loading dock shown

Crews finishing up the truck turn around concrete paving; this area will allow full access to the load dock for delivery to the building as it is now completed.

 

Curbing Crews Working on north side of site

Our crews have placed curb on the North side of the building and in the eastern side of the parking lot including completing almost 3,000 linear feet in one day.

 

Excavation for raft footing

Crews are excavating for the raft foot to support the basket wall. This leg of the wall runs to approximately where the trucks are sitting in the picture. At that point the wall changes to a concrete-covered soil nail wall.

 

Site Overview of Civil Operations

The construction of bridge and wall backfill areas are shown above as crews perform their various assigned tasks.

 

Entrance and Blade Tower

The blade tower and front entrance is nearing completion. EIFS was finished last week and now the crews are working on the metal studding for the façade and over the entrance area.

 

Left side and rear of building

The rear and side elevations were finished and the fine grading near completion around the building. There is still a lot of work to be done, but Gastonia takes one more step towards completion each day.

Progress in all areas of Gastonia

 

Area shown is one of two islands in the parking lot

There are two long “islands” that were prepped for curb pouring. These islands will separate the two parking lots at Gastonia.

 

New utility poles shown before lines are relocated.

The relocation by AT&T of the utility service will have to be completed before the widening of Cox Road and new sidewalk construction can be completed.

 

Excavator placing fill material

 

Fill Material Shown here

Crews used an excavator with a 60’ long reach to place the fill material between the 78’ wide arches. The photo above shows the various materials and the need for some of the work to be done by hand.

 

A top view of the raft footing at the south side of the arches

The raft footing that started last week has 4’ of washed stone and 4 layers of grid inside. The 23’ high wall will be constructed on top of this footing.

 

Crews prep for a pour near the loading dock

First pour of concrete for Truck Turn Around Area.

Sitting on 6” of stone, the concrete slab for the truck turn around area got its first pour. This is the first of the +/-400cy of 4500psi concrete that is required for truck turn around area.

 

Walk-in Storage Cooler installed

Cooler/walk-in storage has been installed and the next step includes installing quarry tile and stainless base/trim.

 

Metal Stud Installation

Metal studs were installed at the front Guest Services area. Once completed, the electrical work will begin and then the area will be finished by the sheet rock and paint crews.

 

Duct Work Installed

Duct work in the front vestibule area was completed and wrapped. The metal stud installation shown on the right in the photo above was completed as well and sheetrock crews will be the next in this area.

 

EIFS work shown on external of building

The blade tower section of the building received EIFS this past week and is ongoing. This area, on the left side of the building, is where the signage will eventually be installed.

Civil & Building Improvements Continue

Fabric installed by civil crew

Raft Footing being installed which consist of a rip rap layer, fabric and stone to support the gabion walls.

 

Spreading rock in footing area

Installation of stone layer within the raft footing. The 4’ thick raft footing will support a 22’ high gabion wall when completed.

 

Crew members laying geogrid material

Footing area after geogrid installation

Geogrid, a high-tensile plastic mesh, is a major component of this work. These 2 layers of basket wall will be covered once the slope grades are finished.

 

Masonry work going up

Prep and Paint of front entrance

On the building side of things, masonry work is ongoing. As the masonry work is being completed, the entrance and feature wall of the building is prepped for paint.

 

Planter 1 poured and irrigation installation shown

Planter 2 prep work before pour

The site will feature planters near the entrance area of the building. Planter 1 was poured and stone caps installed with irrigation installation started. Meanwhile, Planter 2 was prepped for the concrete pour and irrigation will follow.

 

Stone laid of Subgrade for drive to loading dock

Loading dock area after pressure washing & paint prep

The loading dock is getting closer to finishing as our crews spent the week grading the drive. Stone was placed at the Subgrade level and the civil completed for access. The actual loading dock area was pressure washed and prepped for paint.

 

Conduit Installation on site

In other areas of the site, the electrical crews neared completion of the conduit runs and tying into the main power

 

 

 

The Building Pad Turns Over & Pile Driving Begins

With the turnover of the building pad this week, our crews have narrowed down the requirements for turn-over. Stone access road was installed around the building pad and in staging area. Our building superintendent is now on the job to start vertical construction.

We have now shifted the focus from the pad completion to the remainder of the site. Sixteen trucks cycled at a rate of 1.5 rounds an hour as we concentrate efforts to removing about 30,000 CY of overburden that overlays the fill needed to complete the balance of the grading operation.

Our work continues on the spine road through the site and this week we started driving steel H piles and as soon as they are complete we will form and pour reinforced concrete caps to support the double arch culvert bridge crossing Duharts Creek.

Fine Grading Operations have begun, no thanks to the weather!

We have been working a seven day work week the last couple of weeks to get the fill material finished for the pad and staging area, followed by the fine grading operation.  The only exception when delayed by the ice and snow of last week.

We have now completed the sheet piling that surrounds the bridge footings and will start driving “H” piles the first of this week. De-water of the area is the main operation for now.

Our Utility crews have been doing double duty to get the water and storm in around the building.