Gastonia Redevelopment Moving Toward Completion.

We  are using quick lime to dry the onsite material to make it more compact.

With the exception of 50 trees to be planted along the creek banks, all the planting within the flood plain of the offsite stream has been installed.

We  have finished up to the ½ way mark of the soil nail wall.  Here our team is getting ready to start blowing shotcrete on the wire mesh.

We  have topped out the block in this area and will install the cap block to finish out. They have roughly 150sf of wall left to complete.

The staging area has been graded and the stone placed. This area will be covered with stone and asphalt binder.

Inside, Kydex and paint is going on the walls. The drinking fountain has been installed.

Final touches to the cart corral area are completed and now ready for floor grid.

All the hardware for the exterior doors is installed and secure.