Progress On All Fronts

Crews started the soil nail wall this week. This is the first part of the wall, and provides structure for the concrete that will be poured later.

Crews continue to cover subgrade with stone.

The off-site mitigation work is looking good. All the grading is complete with 75% of the small plantings in place. The larger plantings will be done next week.

Crews started the demolition of the concrete median for the offsite roadway improvements.  The crew will have to work closely with the NCDOT and the resurface contract, to be completed at the same time.

Stone crews yield way to paving crews as the first lift of asphalt is put down in the parking lot.

Concrete and Metal Installed at Gastonia

 

Crews installing concrete pipe

Storm crews installing storm pipe through the basket wall, which when complete will discharge drainage from nearby areas and to the relocated Duhart’s Creek.

 

Truck turnaround area and loading dock shown

Crews finishing up the truck turn around concrete paving; this area will allow full access to the load dock for delivery to the building as it is now completed.

 

Curbing Crews Working on north side of site

Our crews have placed curb on the North side of the building and in the eastern side of the parking lot including completing almost 3,000 linear feet in one day.

 

Excavation for raft footing

Crews are excavating for the raft foot to support the basket wall. This leg of the wall runs to approximately where the trucks are sitting in the picture. At that point the wall changes to a concrete-covered soil nail wall.

 

Site Overview of Civil Operations

The construction of bridge and wall backfill areas are shown above as crews perform their various assigned tasks.

 

Entrance and Blade Tower

The blade tower and front entrance is nearing completion. EIFS was finished last week and now the crews are working on the metal studding for the façade and over the entrance area.

 

Left side and rear of building

The rear and side elevations were finished and the fine grading near completion around the building. There is still a lot of work to be done, but Gastonia takes one more step towards completion each day.

Loads of Civil Work This Week

Initial work on the basket wall

Civil work this week involved excavating a slope for a 20 foot high gabion-style basket wall. This area will eventually feature a retaining wall for the upper site where the parking lot will be located and the lower area for the recently relocated Duhart’s Creek.

Front side of building & Parking Lot civil work

Landmarks nearing completion this week include the parking lot sub-grade and the block work on the front of the building.

Completed cut slope

On the southwest area of the site, overburden trash is almost completely gone. Nearby, a large cut slope has been seeded and mulched so that landscape efforts can get a head-start.

Grading work in mid-process

Grading work for an area on the site that will be a mitigated wetlands area began on a soil nail wall that eventually will extend vertically down over 20 feet.

Electrical crews installing conduit runs

In addition to the civil work this week, the electrical crews began installation of the conduit runs for the power feeds for the building. These runs will feature over 2,000 linear feet of conduit runs around the building site after completion.