The Building Pad Turns Over & Pile Driving Begins

With the turnover of the building pad this week, our crews have narrowed down the requirements for turn-over. Stone access road was installed around the building pad and in staging area. Our building superintendent is now on the job to start vertical construction.

We have now shifted the focus from the pad completion to the remainder of the site. Sixteen trucks cycled at a rate of 1.5 rounds an hour as we concentrate efforts to removing about 30,000 CY of overburden that overlays the fill needed to complete the balance of the grading operation.

Our work continues on the spine road through the site and this week we started driving steel H piles and as soon as they are complete we will form and pour reinforced concrete caps to support the double arch culvert bridge crossing Duharts Creek.