Gastonia Moving Closer To Finish Inside and Out

 

Front View of Building

All the signs, glass and store front has come together and is complete, with the exception of the feature wall. Sidewalk will be complete soon.

 

Ceramic tile installation

Inside at the food service area, the ceramic tile is almost complete. The projects are beginning to come together and we are seeing more definition due to the completed work.

 

Finished ceramic tile work

As mentioned previously, the food service areas are getting more defined by the finishing touches such as the ceramic tile shown above.

 

Cooler & Freezer area

In addition to the front food service areas, the areas behind-the-scenes, such as the cooler and freezers, also had tile installed.

 

Front Offices of building

Glass has been installed in the office areas up front. The sheetrock and mud are almost complete and will be ready for the painters soon.

 

Pole relocation process

Steady work continues on the offsite roadway improvements. Electric crews have almost completed the transfer to the new pole locations.

Civil Crews placing fill

Crews have been placing fill on the west side of the steel arches to build the future roadway up. There is still another 8’-10’ of fill to go in here.

 

Retaining Wall

Wall crews continue to progress with the segmental portion of the retaining wall. They have installed nearly 1,000 sf of block in the past 3 days.

Loads of Civil Work This Week

Initial work on the basket wall

Civil work this week involved excavating a slope for a 20 foot high gabion-style basket wall. This area will eventually feature a retaining wall for the upper site where the parking lot will be located and the lower area for the recently relocated Duhart’s Creek.

Front side of building & Parking Lot civil work

Landmarks nearing completion this week include the parking lot sub-grade and the block work on the front of the building.

Completed cut slope

On the southwest area of the site, overburden trash is almost completely gone. Nearby, a large cut slope has been seeded and mulched so that landscape efforts can get a head-start.

Grading work in mid-process

Grading work for an area on the site that will be a mitigated wetlands area began on a soil nail wall that eventually will extend vertically down over 20 feet.

Electrical crews installing conduit runs

In addition to the civil work this week, the electrical crews began installation of the conduit runs for the power feeds for the building. These runs will feature over 2,000 linear feet of conduit runs around the building site after completion.