Building Pad Turnover Milestone Reached

We reached a milestone last week when we turned over the building pad to our building superintendent which means that we are now going vertical with our buildings.

Last week our site crews completed one head wall of the triple 72”’s  storm pipe, that you see below, and have now moved to the next one.

Our foundation crews for the bridge were able to pour one of the bridge footings the first of the week, worked through the week driving H piles and formed the east footing for a Friday evening concrete pour.

The site has changed significantly over the past few weeks, despite the challenging weather. Thanks to all that have helped to make our promises kept thus far.

Fill Operations Continue

We were impacted somewhat by the weather events last week but overall had a decent week.  Our fill operation for the pad continued in coordination with overburden removal, which revealed additional good fill material.

The bulk amount of the fill needed for the building pad should be in place mid next week and we will then continue to the parking fields.

We also finished all the 60” CMP portion of the underground detention system. The filtration system is in fabrication and will be on site in January.

The double steel arch bridge, a part of the future Gaston Mall Drive, started this week with the mobilization of the foundation crew.  We have started driving sheet piles around the footing locations of the bridge before the “H” pile installation which will support the concrete footings of the bridge.

Work Continues For Gastonia

The site grading contractor has been taking advantage of the great weather in late October to get a jump on the undercut for the future building pad. Multiple layers of grid and stone are being used to insure a stable building foundation.

Granular Material and Fabric Covering

Through the month of October, the site contractor has progressed with the installation of the triple 72”CMP (Corrugated Metal Pipe). This is being installed to relocate an existing storm stream under the future parking lot area.

Forming of 72" Pipe Collar

The relocation of the existing outfall sewer was a 24/7 operation after finding the condition of the existing VCP pipe. Crews worked round the clock for 7 days to install, test and cut over more than 1200lf of new 18” sewer line.

Sewer Crew Setting Up For Relocation Process

Night Work for Sewer Relocation

The site contractor was able to get the transition collar from CMP to RCP in on the triple 72” pipes before the Thanksgiving Holiday.