Roadway Access to Gaston Mall Nearing Completion

The traffic signal at Franklin Blvd is nearing completion. Our team has installed signal heads.

The thermoplastic pavement markings have been placed on the Spine Road.

The sidewalk has been completed along the south side of the building.

The new roadway is nearing completion. The street lights are in place and the trees have been planted.

Street and Parking Lot Work Nears Completion

Our team has completed final paving on the Spine Road and the guardrail has been installed. Work on street lights and tree plantings is progressing.

In preparation for the new traffic light at the Franklin Road intersection, signal poles have been installed.

Striping and signing are complete in the parking lot. We have also paved the Cox Road entrance and temporarily striped there.

In the floodplain areas, we have finished the plantings.