Gastonia Channels Forward

New channel staked

The channel defining process began with the crews staking out the new channel and started to install the rock vain on the downstream side of the arches.

 

Rock vein installation

Rock vein is installed and the crew is working on the riffle section going under the arch. There will be 13 of these structures to be installed in the new channel.

 

Curb crews pouring concrete

Over 2,000 linear feet of concrete curbs was poured by the Curb crews. There is around 800 linear feet left to pour in the parking lot and will be finished next week.

 

Main Drive of Parking Lot

Fine grade crews are working to get parking lot grades cut and stone placed. This is the main drive on the east side of the parking lot.

 

Glass installation shown

The Storefront is coming along nicely. Glass is being installed, as well as some of the sidewalk signs.

 

Sidewalk for front of building

We are finishing up our sidewalk prep work with lights, tree grates and bollard sleeves.

 

Ceiling Tile Installation

We have also started our tile installation. Once all the pieces have been cut out for columns and sprinklers the tile will go up fast.

 

Food Area Sheet Rock installed

In the Food Ave area sheet rock is up, mud is being applied and paint will soon follow.

 

 

 

 

Progress in all areas of Gastonia

 

Area shown is one of two islands in the parking lot

There are two long “islands” that were prepped for curb pouring. These islands will separate the two parking lots at Gastonia.

 

New utility poles shown before lines are relocated.

The relocation by AT&T of the utility service will have to be completed before the widening of Cox Road and new sidewalk construction can be completed.

 

Excavator placing fill material

 

Fill Material Shown here

Crews used an excavator with a 60’ long reach to place the fill material between the 78’ wide arches. The photo above shows the various materials and the need for some of the work to be done by hand.

 

A top view of the raft footing at the south side of the arches

The raft footing that started last week has 4’ of washed stone and 4 layers of grid inside. The 23’ high wall will be constructed on top of this footing.

 

Crews prep for a pour near the loading dock

First pour of concrete for Truck Turn Around Area.

Sitting on 6” of stone, the concrete slab for the truck turn around area got its first pour. This is the first of the +/-400cy of 4500psi concrete that is required for truck turn around area.

 

Walk-in Storage Cooler installed

Cooler/walk-in storage has been installed and the next step includes installing quarry tile and stainless base/trim.

 

Metal Stud Installation

Metal studs were installed at the front Guest Services area. Once completed, the electrical work will begin and then the area will be finished by the sheet rock and paint crews.

 

Duct Work Installed

Duct work in the front vestibule area was completed and wrapped. The metal stud installation shown on the right in the photo above was completed as well and sheetrock crews will be the next in this area.

 

EIFS work shown on external of building

The blade tower section of the building received EIFS this past week and is ongoing. This area, on the left side of the building, is where the signage will eventually be installed.

Loads of Civil Work This Week

Initial work on the basket wall

Civil work this week involved excavating a slope for a 20 foot high gabion-style basket wall. This area will eventually feature a retaining wall for the upper site where the parking lot will be located and the lower area for the recently relocated Duhart’s Creek.

Front side of building & Parking Lot civil work

Landmarks nearing completion this week include the parking lot sub-grade and the block work on the front of the building.

Completed cut slope

On the southwest area of the site, overburden trash is almost completely gone. Nearby, a large cut slope has been seeded and mulched so that landscape efforts can get a head-start.

Grading work in mid-process

Grading work for an area on the site that will be a mitigated wetlands area began on a soil nail wall that eventually will extend vertically down over 20 feet.

Electrical crews installing conduit runs

In addition to the civil work this week, the electrical crews began installation of the conduit runs for the power feeds for the building. These runs will feature over 2,000 linear feet of conduit runs around the building site after completion.

Footing Crews Laying Foundations…vertical construction starts soon.

This week our footing crews started the foundations for the vertical construction once the pad was completed and accepted.

Our civil work continue to progress in and around the weather cycles. While our foundation crews poured out the east footing early this week for the bridge, the remainder of the crew was finishing up H-piles on the center footing. Our plans are to pour the center footing the first of the week. The arch structure is scheduled for delivery next week with erection to follow.

The concrete crews also poured the headwall for the outlet end of the triple 72” pipes.

Fine Grading Operations have begun, no thanks to the weather!

We have been working a seven day work week the last couple of weeks to get the fill material finished for the pad and staging area, followed by the fine grading operation.  The only exception when delayed by the ice and snow of last week.

We have now completed the sheet piling that surrounds the bridge footings and will start driving “H” piles the first of this week. De-water of the area is the main operation for now.

Our Utility crews have been doing double duty to get the water and storm in around the building.